Testing and Inspection of Emergency Generators
Emergency generators are used to maintain electrical power to facilities and equipment considered important and/or critical to continued plant operations. They may be found in occupancies such as...
Emergency generators are used to maintain electrical power to facilities and equipment considered important and/or critical to continued plant operations. They may be found in occupancies such as data processing, molten materials, communications switching, medical support systems, refrigerated storage and many others. The use of emergency power generators can allow for continuous uninterrupted operations or, if there is insufficient power or no reason to continue full operations, they may allow for an orderly shutdown of most critical systems.
Emergency generators are also commonly required and used to address life safety concerns (hospitals, emergency lighting, fire alarms, exhaust and/or pressurization fans, etc.) associated with a loss of power. NFPA 110 (2016 ed.), Standard for Emergency and Standby Power Systems, defines Level 1 generator installations as those where failure of the equipment powered by the generator could result in loss of human life or injuries. Level 1 installations generally receive a higher frequency of maintenance than Level 2 installations, which is all other generators.
As diesel drive generators are the most commonly found type of generator, this article specifically discusses the diesel engine driven generator.
A new revision of NFPA 110, Standard for Emergency and Standby Power Systems, has been published for 2016. Chapter 8, entitled Routine Maintenance and Operations Testing, provides information on what should be tested as well as the frequency. Maintenance and testing are recommended in accordance with four items: 1) Manufacturer's Recommendations; 2) Instruction Manuals; 3) Minimum Requirements of NFPA 110; and 4) the Authority Having Jurisdiction (AHJ). Although not expressly stated, one may safely assume that the most stringent of these choices will prevail. Frequencies in Chapter 8 and the Appendix information include Weekly, Monthly, Quarterly, Semi-Annual and Annual, with a few exceptions.
From a practical standpoint, the number of frequencies and different items on each frequency is not truly practical for most users. A better suggestion would be that the few quarterly and semi-annual inspection items be completed on the next high frequency (e.g., Monthly), rather than performing separate inspections for these few items.
Inspection and Testing is broken into three component parts as follows:
DIESEL ENGINE (Or other motive driver, such as propane/natural gas engine, steam turbine, gas turbine, etc.)
NFPA 110 (Figure A.8.3.1[a]) provides a checklist detailing the inspection and testing of engine components into four categories:
- Fuel system
- Lubrication system
- Cooling system
- Exhaust system
- Weekly visual inspection to ensure all components appear satisfactory, that the engine compartment is warm and dry, block heater is on as needed, no evident fuel leaks, etc. These functions can be performed by experienced maintenance personnel.
- Monthly operation of the diesel driver with a minimum 30% generator load. Check all fluids, gages and components prior to, during and after testing. These functions can be performed by experienced maintenance personnel.
- Annually check and change engine fluids and service to maintain performance specifications. This servicing would typically be performed by the engine manufacturer's representative.
- Monthly General Inspection for Level 2 (Weekly Level 1).
- Monthly operation under load. Minimum load of 30% nameplate rated kW for 30 minutes at engine temperature; initiate by simulating an outage on Automatic Transfer Switch (ATS).
- Monthly measurement of storage battery electrolyte specific gravity (generally a storage battery system is used in the UPS system, if provided).
- Monthly ATS operation.
- Semi-annual operation of safeties and alarms.
- Annually tighten control and power wiring connections and clean.
- Annual functional testing of circuit breakers, switches, and relays.
- Annual calibration of voltage sensing relays/devices.
- Five years or 500 hours for Level 2, test for wire insulation breakdown (3/500 Level 1).